Windpark Würselen (Germany)

Construction period: 4 weeks
Execution year: 2024
Client: NORDEX
Address: Würselen-Broichweiden, Germany

1x NORDEX N131
1x NORDEX N117

Cable Ducts for NORDEX N131 –  TS106
 
Base Concrete Layer 
 
Center Point 
 
 

Unloading of reinforcement steel

Laydown Area
 
 
 

Reinforcement Steel
B 500

Reinforcement 
 
 
 
Steel laying 
 
 
 
Reinforcement Team 
 
 
 
The inner of the foundation
 
 
 
Massive steel 
 
 
 
Loads transfer section detail
 
 
 
Concrete casting start 05:00 h
 
 
 
Vibrating first lower concrete layer
 
 
 
Filling the massive plate
 
 
 
Test cubes
 
 
 
Smoothing the surface
 
 
 
Finishing the pedestal
 
 
 
Casting complete
 
 
 
Shuttering removed and external earthing ring installed
 
 
 
Foundation for N131 ready for take-over
 
 
 
Ready for backfill
 
 
 
Turbine N131 ready for erection
 
 
 
Starting the next Foundation for N117-TS106 with the ducts preparation anew
 
 
 
Fixing the correct height
 
 
 
Setting up the Anchor Cage …
 
 
 
Starting the laying of the reinforcement …